Milestones
- Community engagement30 Oct 2023
- Detailed design completed30 Jun 2024
- Construction commencement23 Sep 2024
- Construction completion2 Dec 2024
- Practical Completion - 12 December 202412 Dec 2024Upgraded playground facilities include an A Frame Swing, Cluster Climber, Crows Nest, Mini Forest Fort, Pendulum Swing, Raised Tee Pee, Straight Double Swing, Subiaco Climber. The old play equipment that was replaced as part of this project was able to be donated to Rotary Overseas Relocated Playgrounds, diverting these items from landfill and sending them to disadvantaged communities overseas for repurpose. Other park infrastructure delivered as part of this project include, accessible BBQ/accessible picnic table facilities installed to a new permeable paved surface and additional bike hoops and upgraded composite decking under the park London Plane Tree.
Why are we doing this?
In Council’s most recent annual Playground Safety Audit, the play space in Hewison Reserve was ranked 19 out of 60 play spaces requiring upgrades, making it a priority for redevelopment.
The opportunity to upgrade the BBQ to an accessible offering has been included in the project. Including impact attenuating rubber soft-fall within the new playground design, the play space and park will be transformed to a more inclusive facility catering for people across a wide range of ages and abilities.
The impact
Objectives
The park upgrades will include:
- construction of a new play space, including impact attenuating rubber soft-fall allowing for improved accessibility to play equipment
- new play equipment, sourced from sustainable locally grown Australian timber
- extending the existing natural play area
- upgrades to the BBQ area, including an Accessible BBQ and additional accessible picnic tables.
Community Consultation
Community consultation was undertaken on the project in October 2023. Refer to our Have Your Say page for further details: Hewison Reserve Upgrade | Have Your Say Port Phillip
Your feedback has helped shape the upgrade of Hewison Reserve.